← All questionsGS3 · 2013 · Indian Economy ·PPP in Infrastructure
QUESTION 13
GS3
10 marks

Adoption of PPP model for infrastructure development of the country has not been free of criticism. Critically discuss pros and cons of the model.

WRITE IN
7 min
200 words

Join daily PYQ on Telegram ↗

What the examiner wants

Critically discuss the advantages and drawbacks of the PPP model for infrastructure.

Critically discussDiscuss both sides with evidence, then give a reasoned verdict. More on “critically discuss”

Demand-wise check

  1. 1Pros: private capital and efficiency, risk sharing, faster delivery≈35 words
  2. 2Cons: aggressive bidding, renegotiation, land delays, stalled projects, NPAs, user charges≈35 words
  3. 3Examples: airports (Delhi, Mumbai), highway BOT failures≈35 words
  4. 4Reforms: HAM (2016), independent regulator, dispute resolution≈35 words

Open in about 30 words and close in about 30.

Answer plan

PPP conceptProsConsExamplesReforms

Where marks usually go

  • Not naming failures, e.g. BOT highways stalled after traffic shortfalls around 2012
  • Missing Kelkar Committee (2015) and Hybrid Annuity Model fixes

Draw this

  • Risk table: risk (land, construction, traffic, financing) → public or private bearer under BOT vs HAM

Value addition

  • CommitteeKelkar Committee (2015) recommended amending the PC Act and creating 3P India.Kelkar Committee, 2015
  • ModelHybrid Annuity Model (2016) has government pay 40% of project cost during construction.MoRTH, 2016

Topper copies