← All questionsGS3 · 2014 · Environment ·Pithead Thermal Plants' Environmental Impact
QUESTION 11
GS3
12.5 marks

Environmental Impact Assessment studies are increasingly undertaken before a project is cleared by Government. Discuss environmental impacts of coal-fired thermal plants located at coal pitheads.

WRITE IN
9 min
200 words

What the examiner wants

Discuss the environmental impacts of coal power plants sited at coal pitheads, the kind EIA should capture.

DiscussExplain the different sides of the issue, use evidence, and finish with a balanced view.

Demand-wise check

  1. 1Why pithead: saves coal transport cost, but concentrates mining and burning in one area (Singrauli, Korba, Talcher, Angul)≈30 words
  2. 2Air: fly ash and PM from high-ash (30-45%) Indian coal, SO2, NOx, mercury; cumulative load with mine dust≈30 words
  3. 3Water and land: large water draw from rivers/reservoirs (e.g. Rihand), thermal discharge, ash pond breaches and leachate with heavy metals, land under ash dykes and overburden≈30 words
  4. 4Health and ecology: respiratory disease, fluorosis/mercury in food chain, forest loss and displacement of tribals≈30 words
  5. 5EIA gaps and fixes: cumulative and carrying-capacity studies, FGD, ESPs, dry ash handling, 100% ash use, zero liquid discharge≈30 words

Open in about 30 words and close in about 30.

Answer plan

Why plants are at pitheadsAir, water, land impacts specific to clustersHealthEIA gapsMitigation

Where marks usually go

  • Writing general coal pollution points without the cumulative 'cluster' effect of mines plus plants
  • Ignoring ash pond failures, the most visible pithead problem

Draw this

  • Map of the Singrauli-Sonbhadra cluster showing mines, plants, Rihand reservoir and ash ponds

Value addition

  • ExampleAsh dyke breaches at Essar's Mahan and NTPC Vindhyachal (2019) and Reliance Sasan (2020) in Singrauli flooded villages with fly ash.Singrauli incidents, 2019-20
  • PolicyDecember 2015 emission norms set SO2, NOx and mercury limits for thermal plants; FGD deadlines have been extended several times.MoEFCC, 2015
  • PolicyFly ash notification (1999, amended 2021) requires plants to achieve 100% ash utilisation within set cycles.MoEFCC