← All questionsGS3 · 2026 · Science & Technology ·Fast Breeder Reactor
QUESTION 6
GS3
10 marks

Distinguish between a Fast Breeder Reactor (FBR) and a thermal nuclear reactor. In the context of first indigenously developed prototype FBR at Kalpakkam, explain the term ‘criticality’. What are its implications for clean energy future of our country?

WRITE IN
7 min
150 words

Join daily PYQ on Telegram ↗

What the examiner wants

Contrast fast breeder and thermal reactors, define criticality precisely, and explain what PFBR's 2026 criticality means for India's three-stage, low-carbon nuclear path.

DistinguishBring out the differences clearly, point by point. More on “distinguish”

Demand-wise check

  1. 1Compare: fast vs slow neutrons, no moderator vs water/graphite moderator, liquid sodium vs water coolant, breeding more fuel vs consuming it≈30 words
  2. 2Define criticality: effective multiplication factor k = 1, a steady self-sustaining chain reaction, usually first reached at low power≈30 words
  3. 3Place PFBR as Stage II: MOX fuel, U-238 blanket breeding Pu-239, later thorium blanket producing U-233 for Stage III≈30 words
  4. 4Implications: more energy from scarce uranium, thorium pathway, firm low-carbon baseload; caveats on sodium safety, cost and two decades of delay≈30 words

Open in about 20 words and close in about 20.

Answer plan

FBR vs thermal tableCriticality (k = 1)PFBR milestone and three-stage logicClean-energy implicationsSafety and cost caveats

Where marks usually go

  • Calling criticality a meltdown or uncontrolled reaction
  • Saying a breeder makes fuel from nothing, ignoring the fertile U-238 blanket
  • Omitting PFBR's bridging role between PHWRs and thorium reactors

Draw this

  • FBR vs thermal table plus a sketch of core and blanket showing U-238 → Pu-239 breeding

Value addition

  • DataThe 500 MWe PFBR at Kalpakkam, built by BHAVINI, attained first criticality on 6 April 2026; it uses uranium-plutonium MOX fuel, liquid-sodium coolant and a U-238 blanket.Department of Atomic Energy — PFBR attains first criticality, April 2026
  • DataIndia's nuclear capacity stood at 8.78 GW in June 2026, against the Nuclear Energy Mission target of 100 GW by 2047 announced in the 2025-26 Budget.MNRE Rajya Sabha reply, July 2026; Union Budget 2025-26